The hybrid inverter SAJ H1-3k-s2 is a team single-phase of 3 kW to Low voltage lithium batteries 48 V, which is supplied in this pack with the Chint DDSU666 meter and its 100 A power transformer To manage self-consumption and zero pouring. Integrates 2 MPPT, it admits 4500 WP of panels with a MPPT range of 90 to 550 V and loading or unloading the battery with up 60 a by Load control in 3 stages. Before a network cut, its function UPS commute 10 ms or less and feeds the critical charges with 3000 VA continuous 3600 goes from peak for 10 s. With 97.6% maximum efficiency, 94.6% of battery charge efficiency, adjustment of the Peak-valley period To take advantage of rates with time discrimination and a design fanned below Dba, It is a very complete option for housing. Has protection Ip65 and meet RD 1699, UNE 206006 and UNE 206007.
Photovoltaic entrance (DC)
- Maximum FV power: 4500 WP (STC)
- Maximum DC voltage: 600 V
- MPPT voltage range: 90 to 550 V
- DC nominal voltage: 360 V
- Activation voltage: 120 V
- Minimum DC voltage: 80 V
- Maximum input current DC: 12.5 / 12.5 A (according to technical sheet)
- Maximum short circuit current: 15/15 (according to technical sheet)
- MPPT number: 2
- DC switch: integrated
Drums
- Type of battery: lithium
- Nominal voltage / range: 48 V / 42 to 58.5 V
- Charging / unloading current: 60/60 A
- Control of the load mode: 3 stages
AC output network
- Nominal AC power: 3000 W
- Maximum output power AC: 3000 VA
- Nominal current (230 Vac:) 13.1 A
- Maximum current AC: 13.6 A
- Voltage / range: 220/230/240 V; 180 to 280 V
- Frequency: 50/60 Hz ± 5
- Power factor: 0.8 capacitive to 0.8 inductive
- Thdi: less than 3%
- Connection: L + NO + PE
Backup output (back-up)
- Nominal output power: 3000 VA
- Apparent Power of Peak: 3600 Goes for 10 s
- Output voltage: 220/230/240 V
- Frequency: 50/60 Hz ± 5
- THDV (Linear Load:) less than 3%
- Switching time UPS: 10 ms or less
Efficiency
- Maximum efficiency: 97.6%
- European efficiency: 97.0%
- Maximum battery charge efficiency: 94.6%
Protections and functions
- Short BC and overload: integrated
- Overvoltage / substation DC and AC: integrated
- Overfrequency / subfrequency AC: integrated
- Adjusting the Pico-valley period: integrated
- Drop zero: compatible (with meter)
Interface and general data
- FV connection: MC4
- Battery connection: terminal block
- Display: LCD
- Communication: Wi-Fi / Ethernet / 4G (optional)
- Operating temperature: -25 at +60 ° C (power reduction of 45 to 60 ° C)
- Refrigeration: natural convection, no fan
- Humidity: 0 to 100% without condensation
- Altitude: 4000 m (reduction above 3000 m)
- Noise: less than 29 DBA
- Degree of protection: IP65
- Dimensions (at x an x PR:) 470 x 470 x 190 mm
- Weight: 23 kg
- Warranty: 5/10 / 15/20 (according to option)
- Rules: IEC 62109-1 / 2, IEC 61000-6-1 / 2 / 3/4, EN 50438, EN 50549, C10 / C11, IEC 62116, IEC 61727, RD 1699, UNE 206006, UNE 206007, CEI 0-21, AS 4777.2, CQC NB / T 32004, VDE-AR-N 4105
Pack content
- 1 hybrid inverter SAJ H1-3K-S2
- 1 chint DDSU666 Energy Meter
- 1 current transformer (CT) of 100 A
Benefits Hybrid Inverter SAJ H1-3K-S2
Low voltage hybrid: freedom to choose battery
Unlike high-voltage hybrids, H1 works with 48 v batteries rank 42 to 58.5 V), the most widespread standard in residential storage. This allows you to combine it with lithium batteries modular 48 V and expand capacity by adding parallel modules, provided that the battery is compatible with the communication protocol of the inverter.
Backup before blackouts in 10 ms
The function UPS commute 10 ms or less, such a short time that computers, routers or alarm systems do not get out. In Support mode 3000 VA continuous 3600 Goes from peak for 10 s for the boot of refrigerators or pumps.
Savings with rates for schedules schedules
The function of adjusting the peak-valley period it allows you to schedule the battery charge in the cheapest times and its download on the most expensive, a very cost-effective strategy with rates with habitual time discrimination in Spain.
Zero pouring with the chint ddsu666 meter
The included meter measures imported energy and exported at the connection point. With that information, the inverter prioritize self-consumption, load the battery with surpluses and can apply zero when the installation is not welcomed to compensation. The current transformer 100 A it is placed around the driver without cutting it.
Silent and suitable for outdoor
Thanks to his design without fan and refrigeration by natural convection, your sound level is less than 29 DBA. With protection IP65 and a rank of operation -25 at +60 ° C, can be installed in garages, facades or terraces.
Design of a system with SAJ H1-3K-S2
Photovoltaic field
With 4500 WP maximum 2 MPPT, the inverter it allows to distribute the panels in two orientations. Choose your solar panels and the structures for solar panels suitable for your deck.
Battery capacity
With a stream of 60 A to 48 V, the inverter you can upload and download the battery with a power of some 2.9 kW as a guidance calculation. For most homes with this inverter, a battery between 5 and 10 kWh it covers nocturnal consumption and leaves reservation for network cuts.
Alternatives
If you prefer an all-in-one solution with stackable high-voltage battery, compare with the series SAJ HS2 in our category of inverters hybrid, or check our solar kits with Battery. On Tienda Solar we advise you throughout the process and in the Blog Tienda Solar you will find technical guides prepared by experts.
Frequently Asked Questions (FAQ)
1. What batteries are compatible with the SAJ H1-3K-S2?
Batteries low voltage lithium of 48 V, with a range of 42 to 58.5 V. It is essential that the battery is compatible with the communication protocol of the inverter; consult with our technical team the list of validated models by SAJ.
2. What is the difference between the SAJ H1 and the SAJ HS2?
The H1 work with external low voltage batteries (48 V), while the HS2 is a system all in one of high voltage with BU2 battery modules stackable. H1 offers more freedom to choose battery; The HS2, a more integrated installation.
3. Does it work during a light cut?
Yes, as long as there is installed battery. The backup delivery delivery 3000 VA continuous 3600 Goes from peak for 10 s, with a switching time of 10 ms or less.
4. What is the Chint DDSU666 meter for?
Allows the inverter know in real time the energy that enters and leaves the network, for prioritize self-consumption, load the battery with surplus and apply zero if necessary.
5. Can I charge the battery with the network at the Valley Time?
Yes. The inverter has adjusting the peak-valley period, which allows you to program the load in the cheapest hours and download at peak hours.
6. How many panels can I connect?
Until 4500 WP scattered in 2 MPPT, with a range of 90 to 550 V and a maximum tension of 600 V. The number of panels depends on its power and voltage.
- Power (kW)
- 3 - 5.9
- Phase Type
- Single phase
- Max Current Input (A)
- 12 - 12.99
- Compatibility list
- Pylontech Force L2
Pylontech US2000C / US3000C / US5000
Pylontech US3000C
Pylontech US5000 / Force L2
SAJ B1 / AS1-3KS